[CLOSED] PUBLIC COMMENT ON PROPOSED PROJECT PDD ID030 "Installation of all-electric injection molding machine with power regeneration to plastics & packaging manufacturing plants"

The draft PDD was submitted to the JCM secretariat between Indonesia and Japan on 18 November 2022.
The JCM secretariat of Indonesian and Japanese side makes the draft PDD publicly available for public comments in line with subsection 1.6.1. of the Joint Crediting Mechanism Project Cycle Procedure.

Information on the proposed project below is available for download.

All stakeholders are invited to provide their comments on the proposed project to the following both two email addresses id-pdd-pi@jcm.go.jp; secretariat@jcmindonesia.com only in English, including the following information:
- Name:
- Affiliated Organization:
- E-mail:
- Country:
- Part of the document (A/B/C/etc):
- Page of the document:
- Comment on the page:

NOTE: The secretariat makes all received comments publicly available unless the TPE determines that the comment is unauthentic in line with paragraph 42 of the Joint Crediting Mechanism Project Cycle Procedure.

This call for public comments is open from 23 November 2022 to 22 December 2022 (24:00 GMT).

Project title

Installation of all-electric injection molding machine with power regeneration to plastics & packaging manufacturing plants 
Ref No. ID030
PDD 
Monitoring Plan

Name of project participants (Indonesia) PT Dynaplast; Project location 1. Dynaplast; Project location 2. Sanpak Unggul; Project location 3. Dynaplast Jatake; Project location 4. Rapidplast Plant2; Project location 5. Rapidplast Plant4; Project location 6. Dynaplast Plant8; Project location 7. Dynaplast 4
Name of project participants (Japan) Tokyo Century Corporation
Name of third party entity (TPE) TPE-ID-003 Japan Quality Assurance Organization
Location of project

Country: The Republic of Indonesia
Region/State/Province etc: Project location 1. Bogor, Jawa Barat 16820; Project location 2. Bogor, Jawa Barat 16964; Project location 3. Kota Tangerang, Banten 15135; Project location 4. Sidoarjo 61256, East Java; Project location 5. Pasuruan, Jawa Timur 67161; Project location 6. Bekasi, Jawa Barat 17530; Project location 7. Bekasi, Jawa Barat 17530
City/Town/Community etc: Project location 1. Jalan Raya Narogong Km. 19, Dayeuh, Cileungsi, Pasir Angin, Cileungsi,; Project location 2. Jl. Pancasila IV No.KM. 9, Cicadas, Raya,; Project location 3. Jl. Industri Raya II No.9, Pasir Jaya, Kec. Jatiuwung,; Project location 4. Jln Berbek Industri V/21,; Project location 5. Jl. Raya Malang - Pasuruan No.97, Palang, Lemahbang, Kec. Sukorejo; Project location 6. Jalan Jababeka VI Raya Blok C No.7, Cikarang Utara, Pasirgombong, Kec. Cikarang Utara; Project location 7. Jl. Inspeksi Saluran Kalimalang RT.01 / RW.01, Sukadanau, Kec. Cikarang Barat
Latitude, longitude:
Project location 1. S 6°21′34″ E 106°57′55″; Project location 2. S 6°24′46″ E 106°55′49″; Project location 3. S 6°11′25″ E 106°33′11″; Project location 4. S 7°19′57″ E 112°45′29″; Project location 5. S 7°42′16″ E 112°44′44″; Project location 6. S 6°15′52″ E 107°11′18″; Project location 7. S 6°15′11″ E 107°5′40″

Duration Starting date of project operation: 28 Mar 20
Expected operational lifetime of project: 8 years
Methodology No.

ID_AM025 Ver1.0

Emission Reductions

Estimated emission reductions in each year
- (in 2013)
- (in 2014)
- (in 2015)
- (in 2016)
- (in 2017)
- (in 2018)
- (in 2019)
2,273 (in 2020)
2,973 (in 2021)
2,973 (in 2022)
2,973 (in 2023)
2,973 (in 2024)
2,973 (in 2025)
2,973 (in 2026)
2,973 (in 2027)
700 (in 2028)

Status PDD and MOC submitted

 